We were called in to finish — and make safe — what someone else left standing on scaffolding.

A helical steel staircase, fabricated and erected by another contractor, could only stand because it was propped on temporary works. Under a single person walking, it visibly moved. CAworks was engaged to take ownership of an unfinished, unstable structure and deliver it safe, code-compliant and beautiful. This is how.

3
flights, ~13 m rise
~79
oak-clad steps
Ø610
central steel mast added
2.25
min. factor of safety
10.08 Hz
1st natural frequency

The brief

An unfinished structure, held up by temporary props


The staircase at the heart of this residence was built and installed before CAworks was involved. When our engineer first walked the site, the helix stood only because scaffolding and auxiliary props were carrying its load and restraining it from twisting.

Under controlled walking tests the structure showed global vibration, perceptible torsional flex and audible joint movement. There was no central column and no clear, continuous load path; the segmented stringers had been welded together on site with no weld procedures, no inspection records and no verification of the anchors fixing it to the slabs.

Our remit was unambiguous: assess it honestly, then engineer, document and rebuild it into a permanent staircase that is structurally sound, fully compliant with the Dubai Building Code, and worthy of the architecture around it.

As-found risk rating: HIGH

As-found helical steel staircase encased in temporary scaffolding
As found on site — the bare steel helix carrying load through temporary scaffolding and props.

How we work

From assessment to a finished staircase


A single accountable team carried the project through five phases — diagnosing the problem, engineering and proving the fix, securing authority approval, then fabricating and finishing to a luxury standard.

Phase 01

Assess & advise

Site inspection, professional structural opinion and conceptual reinforcement options.

Phase 02

Survey & engineer

3D laser survey, remediation design, a verified 3D model and full FEA calculations.

Phase 03

Compliance & authority

Dubai Building Code assessment and the submission pack for the design NOC.

Phase 04

Detail & fabricate

Shop drawings, workshop steel fabrication, oak treads and curved toughened glass.

Phase 05

Install & finish

Erection, balustrade and handrails, cladding and final paint finish.

The as-found inspection walkthrough — recording the structure's geometry and behaviour on site before any work begins.
Step 01 — Site inspection

Seeing the problem before touching it


Every rescue starts with a non-intrusive inspection. We record the as-found geometry and behaviour, walk the structure under load, and listen — joint noise and movement tell you as much as deflection does.

Critically, we do not remove the temporary supports. At this stage the props are the only thing preventing torsional rotation and overload of the anchors, so they stay in place until an engineered solution is designed and built.

Step 02 — Professional opinion

A written, signed structural opinion


Before proposing any fix, CAworks issued a formal Professional Opinion — Condition Assessment & Structural Adequacy Review, prepared by a chartered engineer. It documents what was observed, classifies the risk, and sets out conceptual reinforcement strategies — without yet committing to a design.

The conclusion was direct: in its as-found configuration the staircase was structurally unstable without its temporary supports, with a real risk of progressive connection failure if they were removed. The full document is reproduced below with client details removed.

↓ Download the full opinion (PDF) 16 pages · client-anonymised
Step 03 — Concept options

Five ways to make it stand on its own


Rather than jump to one answer, we set out the realistic reinforcement strategies, each with its structural logic and its impact on the architecture — so the design conversation could be had on engineering terms.

Option A — Lateral fixing to structural walls

Rigid connections tie the stringers back to the reinforced-concrete walls, cutting the cantilever span and restraining torsion. Concealed behind cladding to suit the architecture.

Option B — Central / vertical support column

One or more steel columns carry vertical load directly to the slab, all but eliminating cantilever action and global deflection. Clad or decorated to match the design intent.

Option C — Suspended rods from above

Steel tension rods hung from a new structural beam transfer vertical and torsional load upward. Effective, but dependent on new primary steel overhead.

Option D — Reposition to engage a wall

Shifting the helix to bear against a structural wall gives a direct, redundant load path without visible lateral ties — at the cost of moving the architectural set-out.

Option E — Tread stiffening + added stringer

Welded triangular stiffeners under each tread and a second outer stringer raise local rigidity. A complementary measure, recommended alongside one of the primary schemes.

The direction taken. The remediation combined a central structural mast (Ø610 × 14.3 mm CHS) with radial support arms and welded brackets — an Option B-style spine that gives the helix a clear vertical load path — reinforced by tread-level stiffening and an outer stringer anchored back to the wall. It removes the torsional instability at its root while staying invisible behind the finished treads and glass.

Step 04 — Scope of works

What the rescue actually involved


A single scope took the staircase from survey to a finished, certified installation — engineering, reinforcement, and the full architectural finish.

Work packageDescriptionQty
Survey & design
Design
  • Site preparation & set-out for 3D scanning
  • Detailed 3D laser scan / survey of the as-built structure
  • 3D model for client & architect approval (up to two design revisions)
  • Full fabrication drawing set
  • Structural engineering calculations confirming every connection
1
Project management
Labour
Specification, design & fabrication management, production and installation supervision.1
Staircase reinforcement
Metalwork
On-site and workshop steelwork to reinforce the existing structure and limit deflection — the central mast, brackets and stiffening.1
Hardwood oak step cladding
Timber
  • Top- and bottom-shaped solid oak steps
  • 20 mm hardwood, stained / varnished to selection
~79 steps
Curved glass balustrade
Glass
  • Tempered, polished, clear laminated glass
  • Installed into bespoke slotted metal brackets
  • Final thickness to technical design (17.5 mm)
~62 LM
Finishing
Paint
Polishing, priming and painting the steelwork to a selected RAL colour.3 flights
Stringer cladding
Detail
Cladding the stringers to conceal connections for a seamless finished line.3 flights

Commercial figures are intentionally omitted from this case study.

Step 05 — 3D laser survey

Measuring reality, not the drawing


A hand-built, segmented, site-welded staircase never matches its original drawings. Segments drift during erection, welds pull the geometry, and the surrounding slabs and walls are rarely exactly where the architect's model says. To engineer a fix that actually fits, we first capture the structure as it truly is.

A 3D laser scanner (LiDAR) sweeps the space, firing hundreds of thousands of pulses per second and timing each reflection to fix a point in space. The result is a dense point cloud — millions of measured points — that we register into a single survey-accurate model. Photogrammetry adds true-colour texture where it helps.

That captured geometry becomes the master reference for the reinforcement design, the FEA model, and the millimetre-accurate detailing of the oak treads and curved glass — eliminating guesswork and avoiding expensive re-work on site.

±2–3 mm
typical point accuracy
sub-mm
survey-grade range
10⁶+
measured points
1:1
as-built → model
Navigating the registered point cloud — millions of measured points captured on site.
Step 06 — Verified 3D model

Explore the engineered assembly


From the survey we rebuild a precise 3D model of the remediated staircase — the central mast, radial arms, helical stringers, treads and balustrade line. Drag to orbit, scroll to zoom.

Loading 3D model…
⟳

The interactive 3D model didn't load — this can happen on a slow or restricted connection.

View drawings instead
Drag to rotate · scroll to zoom · right-drag to pan
Step 07 — Structural calculations

Proving it with finite-element analysis


The remediated design was verified in SOLIDWORKS Simulation against the Dubai Building Code, ASCE 7-16 and Eurocode 1 — five static studies plus a modal analysis, on grade S275JR steel. The full-assembly model identifies the worst-loaded flight; every result is checked against code allowables.

StudyLoad casePeak stressDeflectionMin. FoS
Static 1Dead load — full assembly43.0 MPa (16% of yield)0.94 mm6.39
Static 23.0 kN/m² live — governing122.3 MPa (44% of yield)1.82 mm2.25
Static 33 kN point load — position 167.2 MPa0.64 mm4.09
Static 43 kN point load — position 268.7 MPa0.83 mm4.00
Static 53 kN point load — position 353.8 MPa0.56 mm5.11
Modal1st natural frequencyno footfall resonance10.08 Hz
≤ 275 MPa
allowable stress (S275JR)
≤ ~13 mm
deflection limit (L/300)
> 8 Hz
frequency (DBC)
196.5 kN
vertical support reaction

Every check passes with margin. The lowest factor of safety — 2.25 at a single welded bracket on the middle flight — sits above the residential threshold of 2.0, and the first natural frequency of 10.08 Hz is comfortably clear of the footfall range, so the finished stair feels firm underfoot rather than springy.

Step 08 — Code compliance

Reading the code the way a reviewer will


A staircase passes authority review only if it is assessed clause-by-clause against the right code. Below is the actual reasoning CAworks set out against the Dubai Building Code 2021, Part K (Villas) — shown next to the real regulation pages it relies on.

The train of thought


1 · Classify the stair correctly. This is a helical / curved stair, assessed under clause K.5.5.2.8 (spiral & curved stairs and winders). Because its tread band sits well away from the centre, we tested it against both the spiral and the curved thresholds — and it satisfies both, so the classification debate never changes the outcome.

2 · Confirm it is even permitted. K.5.5.2.1 expressly allows spiral, winder and open stairs in villas for everything except basement egress. This stair serves no basement, so no fire-rated enclosure is imposed by Part K.

3 · Separate requirements from recommendations. Intermediate landings (K.5.5.2.4) are a recommendation for villa flights over 4 m — not a requirement; the 3,660 mm between-landings limit belongs to Part B / the Fire & Life Safety Code and does not apply to villa stairs; the "spiral not recommended as a main stair" line is advisory, not a prohibition. Knowing which is which is what keeps a submission moving.

4 · Report the one genuine conflict honestly. Clause h) wants the outer handrail on the descending user's right; this helix turns the other way, placing the outer edge on the left. Handing is fixed by the direction of the spiral — it can only be "corrected" by mirroring the whole stair, which the architecture won't allow. So we record it as non-compliant as designed and propose a documented mitigation rather than hiding it.

  • ✓
    10 checks — compliant as designed
  • ~
    3 checks — standard verifications closed at shop-drawing stage (handrail geometry, guardrail heights & gaps, tread traction)
  • !
    1 check — stair handing K.5.5.2.8 h): non-compliant as designed, with an engineering-judgment mitigation (continuous handrails both sides + generous tread depth, riser height, width and guarding) put to the authority at design-NOC stage

The regulations themselves


The assessment reproduces every clause it relies on. These are the actual Dubai Building Code pages behind the matrix above.

The compliance assessment


Issued for the project's Consultant of Record to counter-sign and submit — a clause-by-clause matrix, the recommendation-vs-requirement reasoning, and the handing mitigation, all in one document.

Step 09 — Authority submission (NOC)

Why the approval has to be right — and on time


In Dubai, structural and life-safety documentation for a villa staircase is submitted through the project's Consultant of Record for authority review and a design No-Objection Certificate (NOC) before fabrication is released — and a completion certificate is needed at the end. Getting it wrong, or letting it slip, has real consequences.

01 Fabrication can't be released

If the design is rejected or queried, fabrication is held. A structure already on site stays propped, unusable and exposed — exactly the position this project started from.

02 Completion certificate withheld

Without compliant, signed-off staircase documentation, the villa's completion and handover can be blocked — delaying occupancy and final payments across the whole project.

03 Penalties & liability

Unpermitted or non-compliant structural work exposes owner and contractors to municipal penalties, invalidated insurance, and direct liability should the stair ever fail in use.

04 Rework or removal

A stair built ahead of approval may have to be modified — or removed — to satisfy the code: far costlier than engineering and evidencing it correctly the first time.

05 Programme cost

Every week an NOC is delayed pushes the entire fit-out programme, with knock-on standby and re-mobilisation costs across every trade on site.

06 How CAworks de-risks it

We issue the compliance assessment, calculations, GA drawings and glass specification as one coordinated pack — pre-empting the reviewer's questions on landings, classification and handing so the NOC is secured first time.

Step 10 — Shop drawings

A fabrication-ready drawing pack


The engineering resolves into a complete general-arrangement and detail set — plan, elevations, sections A–H, every connection detail, and a 3D isometric set — issued together with the calculations, compliance assessment and glass specification.

Step 11 — Steel fabrication

Rebuilding the steel, properly this time


The remediation steel — the central Ø610 mast, its radial arms and the load-transfer brackets — is fabricated and welded under controlled workshop conditions, a world away from the unverified site welds of the original. Heavy plate is rolled and cut to the helix, segments are trial-assembled, and every bracket is made to carry its tread's load cleanly into the central spine.

This is where decades of curved-staircase fabrication experience matters: getting a multi-segment helix to come together true, with welds that will pass inspection and perform under torsion and fatigue for the life of the building.

CAworks workshop — curved helical staircase fabrication.
Hoisting a curved steel staircase segment into place
Segments craned and set out against the central mast and slab landings.
Step 12 — Steel installation

Erected on a clear load path


The fabricated assembly is installed against its new central mast and the upper and lower slab landings, with the outer stringer anchored back to the structural wall. Only once the engineered structure is carrying load can the original temporary props finally come out — this time with a verified, continuous load path beneath every step.

Step 13 — Tread production

Solid oak, shaped to the helix


Each step is clad in solid French oak, top- and bottom-shaped to follow the curve of the helix, finished at ~30 mm and stained or varnished to the client's selection. Treads are machined to the surveyed geometry so they seat precisely on the steel below, with consistent nosings around the full sweep of the stair.

Machining and shaping the solid oak treads to the surveyed helix geometry.
Step 14 — Glass fabrication

How the curved balustrade is made


Illustrative of the curved-glass toughening and lamination process.

The balustrade is 17.5 mm curved laminated toughened glass — among the most demanding products in architectural glass. It is made in four stages:

  1. Cut & shape. Flat float glass is cut to size and the edges are ground and polished — done before any heat treatment, because toughened glass can never be re-cut.
  2. Curve. Each sheet is heated in a bending furnace until it softens and slumps onto a curved mould machined to the exact radius — here close to R980 — so the curvature is built into the glass itself.
  3. Toughen. The curved pane is rapidly air-quenched (tempered), locking the surface into compression. It becomes several times stronger and, if ever broken, crumbles into small blunt fragments instead of shards.
  4. Laminate. Two curved toughened panes are bonded with a structural interlayer, so the balustrade stays intact and in place even if a pane is damaged.
Finished helical staircase with timber treads and glass balustrade
The finished result — steel, oak and glass resolved into one clean line.
Step 15 — Balustrade, handrails & finishing

From a liability to a centrepiece


The curved glass is set into bespoke slotted brackets along the inner line, with continuous handrails to both sides — satisfying the compliance mitigation as well as the architecture. The stringers are clad to conceal every connection, and the steel is primed and painted to a selected RAL.

What began as an unfinished structure standing on scaffolding leaves site as a structurally verified, code-assessed and beautifully finished staircase — delivered by one accountable team.

Selected work

Helical & curved staircases by CAworks


A representative selection of CAworks helical and curved staircase work — from bare structural steel in the workshop to finished oak and curved-glass installations. These are separate projects shown to illustrate capability, not all the staircase in this case study.

CAworks · Designer Glass & Structural Staircases

Inspect. Engineer. Fabricate. Finish.


One team accountable for the structure and the finish — from a propped, unsafe staircase to a certified, beautiful one.